Commissioners Court - Special Meeting


Return to the Agenda
AI-3849 4.D.1.       
Meeting Date: 11/16/2012  
Calderon Building Mechanical Equipment Upgrades-Change Order No. 1
Submitted By: Mario Garza, Public Works
Department: Public Works  

Information
RECOMMENDATION
Discuss and consider approval of Change Order No. 1 to the Malek, Inc. contract for the Calderon Building mechanical equipment upgrades.
BACKGROUND
On November 30, 2011 Nueces County entered into a contract with Malek, Inc. for the Calderon Building mechanical equipment upgrades project.
DISCUSSION
Change Order No. 1 allows for the installation of one 110-volt circuit for the new chiller chemical feed panel and replaces an existing HOA (HAND-OFF-AUTO) motor starter switch.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Fiscal Impact:
$1,360.00 *

* Funded from project # 19153401 (Calderon Building Mechanical Upgrades-$23,443.40 balance)

Attachments
Change Order No. 1


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2021 Destiny Software Inc. All Rights Reserved.