AI-12230 4.C.6.       
Meeting Date: 07/29/2020  
Certificate of Substantial Completion for the IFB: 3118-19 Nueces County Courthouse ADA - Site Improvements.
Submitted For: Juan Pimentel Submitted By: Veronica Gamboa, Public Works
Department: Public Works  

Information
RECOMMENDATION
Discuss and consider the approval of Certificate of Substantial Completion for the IFB: 3118-19 Nueces County Courthouse ADA - Site Improvements completed by Mako Contracting.
BACKGROUND
On January 22, 2020 Nueces County entered into a contract with Mako Contracting for the Nueces County Courthouse ADA - Site Improvements project.
DISCUSSION
A final project inspection walk-thru was conducted by representatives of Nueces County Public Works, and Mako Contracting. The project was found to be substantially complete.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Attachments
Cert. of Substantial Completion


    