AI-11624 4.C.2.       
Meeting Date: 02/12/2020  
Change Order No. 3 McKinzie Jail Annex Fire Alarm System
Submitted By: Rita Martinez, Public Works
Department: Public Works  

Information
RECOMMENDATION
Discuss and consider approval of Change Order No. 3 for the McKinzie Jail Annex Fire Alarm System Replacement Project.
BACKGROUND
On September 9, 2018, Nueces County Commissioners Court awarded a contract (IFB No. 3078-18) to Circle Industries for the McKinzie Jail Annex Fire Alarm System Replacement Project. This project consists of replacing the existing fire alarm systems installed in the Jail and SATF (Substance Abuse Treatment Facility) portions of the McKinzie Jail Annex with new fire alarm systems.
DISCUSSION

Change Order No. 3 entails extending the construction contract with Circle Industries an additional 60 to complete the project. Most of the work for this project is in areas requiring a county escort. The shortage in county manpower escorts has caused the inability to provide multiple officers to escort for the construction crew has caused a delay in the project progress. These additional days will allow the contractor to complete the work per the construction contract.

Form 1295 Certificate Number 2020-583046 has been filed with the Texas Ethics Commission.

Budget Information
Information about available funds
Budgeted: Funds Available: Adjustment: Amount Available:
Unbudgeted: Funds NOT Available: Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Attachments
Change Order No. 3
HB89 Form - Circle Industries


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2020 Destiny Software Inc. All Rights Reserved.