Padre Balli Park Improvements, Phase 1 Change Order No. 6
Submitted By:
Monica Rodriguez, Coastal Parks
Department:
Coastal Parks
Information
RECOMMENDATION
Discuss and consider the approval of Change Order No. 6 with TBC Commercial Construction LLC, to increase the contract amount relating to the Padre Balli Park Improvements, Phase 1 Project.
BACKGROUND
On February 24, 2016, Nueces County entered into a contract with TBC Commercial Construction LLC for the Padre Balli Park Improvements, Phase 1 Project (IFB NO. 3004-15)
DISCUSSION
Change Order No. 6 compensates the contractor, $169,793.01 for the following changes:
Additional landscape and stabilization added to project - $147,707.63
Additional support to roads, includes geogrid, TX-7, overlapping at these locations and place another 7" of compacted crushed limestone (a total of 12) then the Asphalt Surface.
TX-7 Geogrid - (5) Rolls - $5,000.00
7" Crushed Limestone - (300) Tons - $9,000.00
Fee - $8,085.38
Total Amount $169,793.01
Budget Information
Information about available funds
Budgeted:
Funds Available:
Adjustment:
Amount Available:
Unbudgeted:
Funds NOT Available:
Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Attachments
TBC Construction LLC Change Order No. 6
AgendaQuick ©2005 - 2022 Destiny Software Inc. All Rights Reserved.