County Road 35 Paving Improvements Change Order No 2
Submitted By:
Rita Martinez, Public Works
Department:
Public Works
Information
RECOMMENDATION
Discuss and consider approval of a deductive Change Order No. 2 for the County Road 35 Paving Improvements from Saratoga Blvd. to CR 26 Project.
BACKGROUND
On March 27, 2019, Nueces County awarded a contract to Garrett Construction Company for the County Road 35 Paving Improvements from Saratoga Blvd. to CR 26 Project.
DISCUSSION
Deductive Change Order No. 2 will include charges to Garrett Construction for liquidated damages for days beyond the contractual completion date and cost for re-testing material compaction not meeting the specifications.
1295 Form Certificate No. 2019-568912 has been filed with the Texas Ethics Commission.
Budget Information
Information about available funds
Budgeted:
Funds Available:
Adjustment:
Amount Available:
Unbudgeted:
Funds NOT Available:
Amendment:
Account Code(s) for Available Funds
1:
Fund Transfers
Source of Funds:
2015 CO's
Amount Requested:
($13,190.00)
Fiscal Year:
FY19/20
Fiscal Impact:
Project #19195006 - Pct 2 Road Improvements
54 additional days
Deductive Change Order - $13,170
$11,000 - Liquidated Damages
$ 2,190 - Materials Re-Testing Cost