SUBJECT:
Resolution No. (R)18-14, amending the infrastructure improvement plans supporting development impact fees for Transportation, Parks and Water Utility
RECOMMENDATION:
Staff recommends approval.
EXECUTIVE SUMMARY:
The purpose of this resolution is to amend the Infrastructure Improvement Plan (IIP) supporting development impact fees for the categories of Transportation, Parks and the Water Utility. The reason for the amendment (attachment 1) is that conditions within the community have changed since original adoption of the IIP and the project list needs to be revised.

These changes do not impact the current level of service, nor does it affect the current fee structure.
BACKGROUND OR DETAILED INFORMATION:
Impact fees are a way for local governments to require new developments to pay a proportionate share of the infrastructure costs their projects impose on community service levels. As such, new development pays for its pro-rata share of the cost of new capital facilities to maintain said service levels. These fees are one-time, up-front charges that are assessed on new development. 

State law governing impact fees stipulates that impact fees may only be collected to pay for improvements identified in an adopted Infrastructure Improvement Plan (IIP). So by implication, impact fees can only be spent on improvements listed in the IIP. State law also provides that change may be required and/or allowed during the life of an adopted IIP. This allows the capital plan to change in response to unforeseen development at the time of first adoption, without triggering the need for a complete and comprehensive impact fee update.

The history of the Town's current Impact Fee Schedule and adopted IIP is as follows:
  • 12/04/13 - PUBLIC HEARING: ADOPTING THE 2013-2023 LAND USE ASSUMPTIONS AND INFRASTRUCTURE IMPROVEMENT PLANS FOR THE TOWN'S DEVELOPMENT IMPACT FEE UPDATE STUDIES COVERING PARKS, POLICE, TRANSPORTATION, ALTERNATIVE WATER SYSTEM AND POTABLE WATER SYSTEM DEVELOPMENT IMPACT FEES
     
  • 01/15/14 - RESOLUTION NO. (R)14-07, ADOPTING THE 2013-2023 LAND USE ASSUMPTIONS AND INFRASTRUCTURE IMPROVEMENT PLANS DATED OCTOBER 4, 2013, FOR THE TOWN OF ORO VALLEY

  • 02/19/14 - PUBLIC HEARING: REPEALING AND REPLACING ORO VALLEY TOWN CODE CHAPTER 13 - DEVELOPMENT FEES AND CHAPTER 15, ARTICLE 17 - WATER RATES, FEES AND CHARGES SETTING FORTH STANDARDS AND PROCEDURES FOR CREATING AND ASSESSING DEVELOPMENT IMPACT FEES CONSISTENT WITH THE REQUIREMENTS OF ARIZONA REVISED STATUTES (A.R.S.) SECTION 9-463.05

  • 04/04/14 - PUBLIC HEARING: ORDINANCE NO. (O)14-04, AMENDING THE ORO VALLEY TOWN CODE CHAPTER 13, DEVELOPMENT IMPACT FEES, BY REPEALING CHAPTER 13 IN ITS ENTIRETY AND REPLACING IT WITH A NEW CHAPTER 13 AS PROVIDED IN EXHIBIT "A"
and

PUBLIC HEARING:  ORDINANCE NO. (O)14-05, AMENDING THE ORO VALLEY TOWN CODE CHAPTER 15 ARTICLE 17, WATER RATES, FEES AND CHARGES TO COMPLY WITH NEW CHANGES MADE TO CHAPTER 13, DEVELOPMENT IMPACT FEES
 
This amendment has been noticed to the public for more than 30 days prior to this meeting.
FISCAL IMPACT:
 Since the fee structure remains unchanged, there is no fiscal impact to the budget.
SUGGESTED MOTION:
 I MOVE to (approve or deny) Resolution No. (R)18-14, amending the infrastructure improvement plans supporting development impact fees for transportation, parks and water utilities.
Attachments
Resolution No. (R)18-14 Amending Infrastructure Improvement Plans
Attachment 1 - IIP Amendment


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2020 Destiny Software Inc. All Rights Reserved.