  Agenda Item 2.e.       
Meeting Date: 03/05/2019  
Item Title:    King Mountain Switch Station Engineering and Project Management Services
Submitted By: Jeff Janke
Bid Number: 0540-19

Purchase Justification:
This request provides civil, structural, and design engineering services for the construction of the GP&L King Mountain Switch Station.  The station will be configured as a five-bay breaker-and-a-half switching station, with five 345kV circuit breakers in the first and fifth bays.  The selected firm will also provide project management services and construction activity support before, during, and post-construction.
Evaluation:

Power Engineers was selected as the Most Qualified firm for this project from the short list of consultants evaluated and scored in RFQ 0942-17.

Award Recommendation:
Vendor Item Amount
Power Engineers All $1,172,122.00
     
     
  TOTAL:
$1,172,122.00
Bid Recap Sheet 1
 
OPENED:
REQ. NO.
BID NO.
PAGE:
BUYER:
VENDOR VENDOR VENDOR VENDOR VENDOR
I
T
E
M
Q
T
Y
U
N
I
T
DESCRIPTION UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
      TOTAL PRICE          
NEXT LOW:
LOW:
SAVINGS:
  # IonWave Invitations
# IonWave HUB Invitations
# Direct HUB Invitations
# HUB Responses
Notes:
 
Bid Recap Sheet 2
 
OPENED:
REQ. NO.
BID NO.
PAGE:
BUYER:
VENDOR VENDOR VENDOR VENDOR VENDOR
I
T
E
M
Q
T
Y
U
N
I
T
DESCRIPTION UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
      TOTAL PRICE          
NEXT LOW:
LOW:
SAVINGS:
  # IonWave Invitations
# IonWave HUB Invitations
# Direct HUB Invitations
# HUB Responses
Notes:
 
Bid Recap Sheet 3
 
OPENED:
REQ. NO.
BID NO.
PAGE:
BUYER:
VENDOR VENDOR VENDOR VENDOR VENDOR
I
T
E
M
Q
T
Y
U
N
I
T
DESCRIPTION UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL UNIT
PRICE
TOTAL
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
                           
      TOTAL PRICE          
NEXT LOW:
LOW:
SAVINGS:
  # IonWave Invitations
# IonWave HUB Invitations
# Direct HUB Invitations
# HUB Responses
Notes:
  
Basis for Award: Most Qualified  
Purchase Requisition #: 41201

Fiscal Impact
Total Project/Account: $9,400,000
Expended/Encumbered to Date: 35,830
Balance: $9,364,170
This Item: 1,172,122
Proposed Balance: $8,192,048
Account #: 210-3799-3178001-7111
Fund/Dept/Project – Description and Comments:
Electric CIP / Substations Upgrades - This request provides civil, structural, and design engineering services for the construction of the GP&L King Mountain Switch Station.  The station will be configured as a five-bay breaker-and-a-half switching station, with five 345kV circuit breakers in the first and fifth bays.  The selected firm will also provide project management services and construction activity support before, during, and post-construction.
Attachments
Bid Recap

  
Fiscal Reference:  
Budget Type: CIP
 
Fiscal Year: 2018  
Document Location: Page E10  

Budget Director Approval: Ron Young Approval Date: 02/21/2019
Purchasing Director Approval: Gary L. Holcomb Approval Date: 02/19/2019

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2022 Destiny Software Inc. All Rights Reserved.