Re:    Approval of RFP No. 2018-004 Change Order No. 3 to Gator Dredging for ICWW Dredging
Submitted For: John Andrews

SUBJECT:
Approval of RFP No. 2018-004 Change Order No. 3 to Gator Dredging for the Intra-Coastal Water Way dredging in the amount of $523,900.00.
SUMMARY:
Approval of Change Order No. 3 to Waterfront Properties Services, LLC dba Gator Dredging in the amount of $523,900.00. This is to remove approximately 7500 Cu. yds of spoil material from the Intra Coastal Water Way (ICWW) channel prior to the start of turtle nesting season per the request of the Army Corps of Engineers. Pending final approval of the City Attorney as to form and correctness.
 
RECOMMENDATION:
Approval
ALTERNATIVES:
Seek alternative bids and/or wait to start the project after turtle nesting season next year.
RESPONSIBLE STAFF:
Ed Seissiger, Engineering Project Manager
COORDINATED WITH:
Bret Sap, Project Superintendent Gator Dredging

Fiscal Impact
Budgeted Y/N: N
Fiscal Year: 2019/2020
Account: 401-4100-575-63-20
Amount: $523,900.00
FISCAL IMPACT:
This is a non budgeted item, Army Corps of Engineers has requested it to be completed prior to the start of turtle nesting season.
Attachments
Change order No 3 RFP 2018-004

<
Form Review
Inbox Reviewed By Date
Finance Department Johnna Morris 01/27/2020 10:24 AM
City Manager Nick Mimms 01/28/2020 08:32 AM
Form Started By: Ed Seissiger Started On: 01/14/2020 09:35 AM
Final Approval Date: 01/28/2020

    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2020 Destiny Software Inc. All Rights Reserved.