Meeting Date: 10/19/2021  
Contact: John Crear, Graduate Engineer
Also Contact: Crystal Owens - Director of Development Services
Phone: 972-230-9672  

COUNCIL ACTION
Motion by Councilmember Raphiel with a second by Councilmember Hughes to approve as presented. Motion passes 7-0.
AGENDA ITEM:
Consider authorizing the City Manager to negotiate and execute a professional services contract with Glenn Campbell Engineering, L.P. in a not-to-exceed amount of $108,980 for the design of Shoreline Drainage Project
BACKGROUND:
The public drainage easement between Shoreline Drive and Honey Tree Lane is experiencing extensive erosion issues. The existing cross tie retaining wall structures are exhibiting signs of failure due to degradation of the original wood. These wall failures are resulting in slope failure and erosion at the rear of the properties. 
FINDINGS:
Staff requested a proposal for the project design. Glenn Campbell Engineering, L.P. provided a proposal in the amount of $108,980. 
FINANCIAL IMPACT:
The funding source for this project is American Rescue Plan Act funding provided through the City's share of grant funding provided directly to municipalities. The overall budget for this project is estimated at $700,000 for design and construction, and the City of DeSoto is not required to provide any matching funds. 
RECOMMENDATION:
Staff recommends that the City Council authorize the City Manager to negotiate and execute a professional services contract with Glenn Campbell Engineering, L.P. in a not-to-exceed amount of $108,980 for the design of the Shoreline Drainage Project.
MANAGEMENT REVIEW
Attachments
Location Map
Scope of Services
Fee Breakdown


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2022 Destiny Software Inc. All Rights Reserved.