TITLE:    W.O. 22-10 Alkali Creek Water and Sewer Extension, Consultant Agreement
PRESENTED BY: Debi Meling
Department: Public Works  

RECOMMENDATION
Staff recommends the City Council award a professional services contract for W.O. 22-10, Alkali Creek Water and Sewer Extension, to Morrison-Maierle in the amount of $176,700.
BACKGROUND (Consistency with Adopted Plans and Policies, if applicable)
W.O. 22-10, Alkali Creek Water and Sewer Extension will extend the existing 12- inch water main and the existing 18- inch sanitary sewer along Alkali Creek Road from the intersection of Strawberry Avenue and Alkali Creek Road to the northwest approximately 3,400 feet.  The water and sewer extension will terminate at the property line of the proposed Mitchell Development and allow the Mitchell Development to have City services.  This extension will also be part of the "backbone" of the water and sewer infrastructure needed to serve the Inner Belt Loop Corridor.  The water and sewer extensions are also recommended in the Water and Wastewater Master Plans.

Morrison-Maierle was selected for the project using the proposal process.  Two other proposals were received from Sanderson Stewart and IMEG.  The consultant selection was based on Project Team and Availability; Project Approach; and Firm Qualifications and Experience as related to the project needs.
ALTERNATIVES
City Council may:
  • Approve awarding the Professional Engineering Services Contract to Morrison-Maierle, or;
  • Not approve awarding the engineering contract to Morrison-Maierle. If the project is not awarded, the Mitchell Development will not have City services and will have to develop in the County.  Water and sewer mains to serve the Inner Belt Loop Corridor will not be extended at this time.
FISCAL EFFECTS
The project was budgeted in FY22 using water and wastewater funds.  The amount budgeted is $3,400,000.  This agreement for professional services will use $176,600 of the budgeted amount and the remaining budget will be used for construction.

Attachments
W.O. 22-10 Professional Services Contract


    

Level double AA conformance,
                W3C WAI Web Content Accessibility Guidelines 2.0

AgendaQuick ©2005 - 2022 Destiny Software Inc. All Rights Reserved.